3 BIM
PROCESS AND IMPLEMENTATION
3.1
General
The project BIM
Implementation Plan is intended to be used as a guideline to incorporate BIM as
an integral part of LACCD's design, construction and facilities management processes.
These guidelines shall be considered Project BIM requirements not District BIM
Guidelines. This document represents guidelines for implementation of certain
BIM processes that may be new to the Project Team. Any deviations to the
guidelines outlined herein must be documented by the Project Team, and then
reviewed and approved by LACCD prior to commencement. As technology progresses,
LACCD will work with project teams to update these requirements accordingly.