3.3 Project
BIM Work Plan
Design and Construction teams shall be required to submit to LACCD for
approval, Project BIM Work Plans demonstrating their strategy for using
Building Information Modeling to executing project deliverables.
a. Design BIM Work Plan - As part of their design proposal, The Design Team shall
submit “BIM Work Plan” which shall contain the following:
1.
Proposed BIM Software to be used
2.
Proposed BIM Workshops and Training integrated in
to project schedule
3.
Strategy for compliance with LACCD BIM Project
Requirements (ref. Sec 2 - BIM PROJECT REQUIREMENTS)
4.
Schedule integrating progress BIMs per Design
Document Submission Standards
5.
File formats used for project submittal and file
exchange
6.
File exchange protocol
7.
Strategy for establishing and managing shared file
server (ref. 3.2.2.a)
8.
Strategy for updating and coordinating design
changes during construction using BIM
9.
Documentation of any proposed deviation from BIM
Standards for LACCD consideration
10.
Project team qualifications and experience in BIM,
and a list of individuals with relevant experience assigned to the following
roles:
·
Design BIM Facilitator (ref. Section 3.4.1)
·
Mechanical System BIM Coordinator (ref. Section
3.4.2)
·
Lead BIM Technicians for all major trades (i.e.
Architect, Civil, MEP, Structural)
·
Senior Project Designers and Engineers
·
BIM and IT Managers for all applicable trades
b. Construction BIM Work
Plan -In the Bid,
Contractor shall submit a Construction BIM Work Plan, outlining their strategy
for utilizing BIM Technology to execute construction related activities and
coordination
1.
List of Sub-contractors using digital fabrication
per Section 3.2.4.c
2.
Proposed BIM Software to be used by the GC and
fabrication modelers for approval by LACCD
3.
Proposed BIM Workshops and Training integrated in
to project schedule
4.
Strategy for file exchange and integrating
Construction Management Activities in to Shared File Server
5.
Documentation of any deviation from LACCD BIM
Standards for LACCD consideration
6.
Proposed strategy for utilizing BIM during
construction phase including:
·
Proposed use of digital fabrication to validate
constructability of design
·
Updating as built conditions in Construction
Record BIM
·
Integration of Record information in to
Construction Record BIM
·
Proposed utilization of 4D Scheduling and
Sequencing technology
7.
Project team qualifications and experience in BIM,
and a list of individuals with relevant experience assigned to the following
roles:
·
Construction BIM Facilitator (ref. Section
3.4.1)
·
Lead Fabrication Modelers for all trades in
section 3.2.4.c
Figure 2 – Sample of Project BIM Work Flow