3.3 Project BIM Work Plan

Design and Construction teams shall be required to submit to LACCD for approval, Project BIM Work Plans demonstrating their strategy for using Building Information Modeling to executing project deliverables.

a.     Design BIM Work Plan - As part of their design proposal, The Design Team shall submit “BIM Work Plan” which shall contain the following:

1.     Proposed BIM Software to be used

2.     Proposed BIM Workshops and Training integrated in to project schedule

3.     Strategy for compliance with LACCD BIM Project Requirements (ref. Sec 2 - BIM PROJECT REQUIREMENTS)

4.     Schedule integrating progress BIMs per Design Document Submission Standards

5.     File formats used for project submittal and file exchange

6.     File exchange protocol

7.     Strategy for establishing and managing shared file server (ref. 3.2.2.a)

8.     Strategy for updating and coordinating design changes during construction using BIM

9.     Documentation of any proposed deviation from BIM Standards for LACCD consideration

10.  Project team qualifications and experience in BIM, and a list of individuals with relevant experience assigned to the following roles:

·         Design BIM Facilitator (ref. Section 3.4.1)

·         Mechanical System BIM Coordinator (ref. Section 3.4.2)

·         Lead BIM Technicians for all major trades (i.e. Architect, Civil, MEP, Structural)

·         Senior Project Designers and Engineers

·         BIM and IT Managers for all applicable trades

b.    Construction BIM Work Plan -In the Bid, Contractor shall submit a Construction BIM Work Plan, outlining their strategy for utilizing BIM Technology to execute construction related activities and coordination

 

1.     List of Sub-contractors using digital fabrication per Section 3.2.4.c

2.     Proposed BIM Software to be used by the GC and fabrication modelers for approval by LACCD

3.     Proposed BIM Workshops and Training integrated in to project schedule

4.     Strategy for file exchange and integrating Construction Management Activities in to Shared File Server

5.     Documentation of any deviation from LACCD BIM Standards for LACCD consideration

6.     Proposed strategy for utilizing BIM during construction phase including:

·         Proposed use of digital fabrication to validate constructability of design

·         Updating as built conditions in Construction Record BIM

·         Integration of Record information in to Construction Record BIM

·         Proposed utilization of 4D Scheduling and Sequencing technology

7.     Project team qualifications and experience in BIM, and a list of individuals with relevant experience assigned to the following roles:

·         Construction BIM Facilitator (ref. Section 3.4.1)

·         Lead Fabrication Modelers for all trades in section 3.2.4.c

Figure 2 – Sample of Project BIM Work Flow